
Custom Home Builder Hamilton: Real Costs, Timelines, Permits
Updated October 13, 2026. Building Dreams Contracting Inc., Hamilton, Ontario.
A custom home builder in Hamilton designs and builds a new house on your lot, and manages the City approvals that set your budget and schedule. Beyond construction, the largest single fee is the City development charge, which runs $44,415 to $102,451 on a single detached home before exemptions [1].
TL;DR
In short: the seven facts that change a Hamilton custom home budget or schedule.
Hamilton's development charge on a new single detached home runs $44,415 to $102,451 before exemptions, plus $3,579 in education charges [1].
For a home you will live in, the City portion is paid at occupancy, not when you apply; education charges are due before the permit issues [1].
A demolition credit cuts those charges on a knockdown rebuild for up to five years after the demolition permit [1].
A complete house permit application carries a 10 day decision window under the Ontario Building Code, and the clock starts only once the package is complete [5].
A design outside the zoning rules needs a minor variance from the Committee of Adjustment, followed by a 20 day appeal window [6].
Escarpment lots inside the Area of Development Control need a Niagara Escarpment Commission permit before the City permit [9].
A builder of custom homes on your land must hold an HCRA licence as both builder and vendor; check the Ontario Builder Directory [11].
One liner: In Hamilton, the lot and the approval path set your budget and schedule as much as the floor plan does, so price the charges and permits before the drawings are final.
Key Numbers
In short: every figure on this page, with the source and the period it applies to.
Figure | What it is | Source | Currency |
|---|---|---|---|
$44,415 | City DC, single detached, rural area | [1] | June 1, 2026 to May 31, 2027 |
$81,303 | City DC, Urban Area B, separated sewer | [1] | June 1, 2026 to May 31, 2027 |
$89,729 | City DC, Urban Area A, combined sewer | [1] | June 1, 2026 to May 31, 2027 |
$102,451 | City DC, Urban Area A, separated sewer | [1] | June 1, 2026 to May 31, 2027 |
$3,579 | Education development charges per unit | [1] | June 1, 2026 to May 31, 2027 |
$1,931 | Dundas and Waterdown special area charge | [1] | June 1, 2026 to May 31, 2027 |
20% | Partial DC exemption, to August 31, 2027 | [1] | In force |
4% | Partial DC exemption, to May 31, 2027 | [1] | In force |
5 years | Demolition credit window after the demolition permit | [1] | Current by-law |
10 days | OBC decision window, complete house permit application | [5] | O. Reg. 163/24 |
2 days | Window to declare a permit application incomplete | [5] | O. Reg. 163/24 |
20 days | Minor variance appeal window after the decision | [6] | Planning Act s. 45(12) |
60 days | Notice before demolishing a Municipal Heritage Register property | [7] | Current City guidance |
Feb 1, 2021 | Builder licensing moved from Tarion to the HCRA | [11] | HCRA |
$400,000 | Maximum Tarion contract home warranty coverage | [12] | Tarion |
On many urban Hamilton lots, the City's full development charge for a new single detached home is $102,451 before temporary exemptions [1]. It comes due when you move in. Plenty of early budgets leave that line out. Pricing it with the lot, the drawings and the build, from the first meeting, is the core job of any custom home builder. Hamilton lots make that job harder than most.
Short answer: The price of a Hamilton custom home is the build plus land, design, permits and City development charges. Those charges run $44,415 to $102,451 on a single detached home before exemptions [1]. Design and approvals come first, so your schedule starts well before construction does.
Custom homes in Hamilton don't follow one template. A lower-city infill lot, a wide property on the Mountain, a sloped Ancaster site near the Escarpment. Each one changes the drawings, the approvals and the price. Below, you'll find the City's published numbers where they exist and a clear plan for everything else.
Jump to:
What a custom home costs in Hamilton
How long a custom home takes
Permits, zoning and minor variances
What to check before you sign
Homes we've built around Hamilton
Questions and answers
What a Custom Home Costs in Hamilton
In short: budget five lines. Land, construction, design and engineering, permits, and City development charges. Construction is the biggest, but the development charge in the next section is the one most early budgets leave out [1].
A Hamilton custom home costs the sum of five lines: land, construction, design and engineering, permits, and City development charges. On a single detached home, development charges alone run $44,415 to $102,451 before exemptions, depending on where the lot sits [1]. Construction is the biggest line, but it isn't the only large one.
Permit, Design and Site Costs
Cost line | What moves the number |
|---|---|
Design and drawings | Size, complexity and rounds of revisions |
Engineering, survey and soils | Slope, soil conditions and retaining walls |
Building permit fee | Set per square metre of floor area in the City's fee schedule [2] |
Lot grading and drainage | Lot slope, neighbouring grades and infill conditions |
Water, sewer and utility connections | Distance to services and whether existing connections can be reused |
Demolition | Size of the existing house, materials and disposal |
Conservation authority review | Lots near watercourses, valleys or the Escarpment |
We price every line above during our Plan and Price phase, before construction starts [3]. Want them priced for your lot? Start your project [4].
Development Charges: The Line Most Hamilton Budgets Miss
In short: the City development charge on a new single detached home runs $44,415 to $102,451 before exemptions [1]. For a home you will live in, it is paid at occupancy, and a demolition credit can lower it on a knockdown rebuild.
On urban Hamilton lots, the City development charge for a new single detached home is well above $50,000 before exemptions [1]. For a home you'll live in rather than rent, the City portion is paid in one payment at occupancy, not when you apply [1]. The school board portion is due before the permit is issued.
The rate depends on the lot's area and sewer system:
Rate area | City DC, single detached, full rate (June 1, 2026 to May 31, 2027) |
|---|---|
Rural Area | $44,415 |
Urban Area B, separated sewer system | $81,303 |
Urban Area A, combined sewer system | $89,729 |
Urban Area A, separated sewer system | $102,451 |
Education DCs, all areas | $3,579 |
Dundas and Waterdown special area charge | $1,931 |
Two temporary exemptions reduce the City portion: 20% until August 31, 2027, and 4% until May 31, 2027 [1]. Timing matters as well. The rate is usually set on the date the building permit is issued, and it rises each June 1 [1]. A permit issued after an exemption ends pays more for the same house.
Tearing down an older house first? A demolition credit lowers the DCs on the new home when the old building came down under a demolition permit. The credit covers City and education DCs. It lasts up to five years after the demolition permit is issued, and is valued at the rate in effect when you rebuild [1]. A vacant lot pays the charge in full. A knockdown rebuild with a timely demolition permit pays less. That's why we set demolition and permit dates as part of the budget, not after it.
For a number tied to your exact lot, the City prepares an informational DC estimate on request [1].
Adding a Secondary Suite: An Exemption Worth Designing In
Planning an in-law suite or a basement apartment? The City exempts up to two additional dwelling units ancillary to a detached, semi-detached or row house from development charges in full [1]. That covers new houses as well as existing ones. Two extra units on a new build, and the City development charge on them is nil.
Design is where this gets decided. A suite added after the fact often means reworking stairs, egress windows, fire separation and parking. Drawn in from the start, it costs far less to build and keeps the exemption straightforward.
How Long a Custom Home Takes in Hamilton
In short: design, approvals and construction run in sequence. A complete house permit application carries a 10 day decision window [5], and a minor variance adds a hearing plus a 20 day appeal window [6].
A Hamilton custom home schedule has three stretches: design, approvals and construction. Approvals swing the most, because a design that needs a minor variance adds a hearing and an appeal window before the building permit can move. Here's how the pieces fit.
Phase | What happens | What sets the length | Typical duration |
|---|---|---|---|
Discover and design | Site review, plans, renderings, consultant reports | Design complexity and how quickly decisions are made | Confirmed for your project during Plan and Price [3] |
Minor variance (only if the design needs one) | Committee of Adjustment hearing and decision | The City's hearing schedule, then the appeal window [6] | Hearing date set by the City, plus 20 days |
Building permit | City review of a complete application | Ontario Building Code decision window for a house [5] | 10 days once the application is complete |
Construction | Foundations to finishes, with City inspections at set stages | Size, structure, season and selections | Confirmed for your project during Plan and Price [3] |
Handover | Final inspection, walkthrough and home documents | Deficiency items and final sign-off | Confirmed for your project during Plan and Price [3] |
The permit clock only starts once the application is complete. The chief building official has two days to flag a package as incomplete, and a flagged package falls outside the 10 day window [5]. Other required approvals, such as a conservation authority permit, need to be settled for the permit to issue.
Variances have their own rhythm. After the Committee of Adjustment decides, there are 20 days to appeal to the Ontario Land Tribunal. That right sits with the applicant, the Minister and specified persons or public bodies [6]. Neighbours can no longer file that appeal, which makes the window more predictable than it used to be.
We map this whole path during Plan and Price. Once building starts, BuilderTrend keeps progress visible, so you see each stage as it happens [3].
Hamilton Permits, Zoning and Minor Variances
In short: the building permit comes last. Zoning, heritage, conservation authority and Niagara Escarpment approvals must be settled first, because the City cannot issue a permit while any applicable law approval is outstanding [7].
In Hamilton, the building permit is the last approval in the chain, not the first. Every other required approval, known as applicable law, has to be in place before the City can issue it [7]. The usual order looks like this:
Confirm what zoning allows on the lot: height, setbacks, lot coverage and parking.
Check for other approvals, such as a heritage permit, a conservation authority permit or a Niagara Escarpment Commission development permit [7].
Apply to the Committee of Adjustment for a minor variance if the design doesn't fit zoning [8].
Prepare the permit package: drawings, grading and servicing details, and the application form.
Submit a complete application and answer any review comments [5].
Build, with City inspections at the required stages.
Pass final inspection and receive your home documents.
A minor variance suits a design that sits close to the zoning rules but not quite inside them, like a slightly smaller side yard. The Committee asks four questions [6]. Is the change minor? Is it desirable for the property? Does it keep the general intent of the Official Plan, and of the zoning by-law? A bigger departure usually needs a zoning by-law amendment, which City Council decides.
Planning to replace an older house? If it's on the City's Municipal Heritage Register, the City needs 60 days' notice before demolition [7]. Build that into the schedule before you book the excavator.
Infill, Mountain and Escarpment Lots
Hamilton is one city made of many communities, and the address changes more than the commute. Amalgamation put Ancaster, Dundas, Stoney Creek, Flamborough and Glanbrook inside the same municipality. Rate area and servicing still differ from street to street. That is why the development charge above swings by more than $58,000 [1]. The lot is the brief the architect has to answer.
Lot type | Where this comes up | What we look at first | Approvals that may apply |
|---|---|---|---|
Lower city and infill | Downtown, Westdale, the north end and older east end streets | Tight access, neighbouring homes, existing services, grading against older lots | Minor variance for setbacks or height; heritage permit or 60 day demolition notice for listed properties [7] |
Mountain and suburban | Hamilton Mountain, Stoney Creek, Ancaster, Waterdown, Binbrook | Lot width, grading, drainage and the link between indoor and outdoor space | Minor variance if the design pushes zoning limits; conservation authority approval near regulated land [7] |
Escarpment, valley and rural | Dundas valley, Flamborough, Glanbrook and Escarpment edges | Slope, retaining walls, views, construction access, and servicing on rural lots | Niagara Escarpment Commission development permit inside the Area of Development Control [9]; conservation authority approval [7] |
Escarpment lots need the most care. Inside the Commission's Area of Development Control, a new house needs a development permit unless it's exempt. The City's building permit can only follow it [9]. In those areas, the Niagara Escarpment Plan applies in place of City zoning [10].
Good custom home builders in Hamilton check all of this before drawings are final. We run it during early due diligence, so the design and the approval path move together.
Licensed Design-Build: What to Check Before You Sign
In short: confirm the builder holds an HCRA licence as both builder and vendor in the Ontario Builder Directory, and that Tarion enrolment is confirmed before the construction contract is signed [11] [12].
In Ontario, a company that builds a custom home on land you own must be licensed by the Home Construction Regulatory Authority (HCRA). It needs that licence as both a builder and a vendor [11]. Builder registration moved from Tarion to the HCRA on February 1, 2021, and Tarion now runs the new home warranty program [11]. Some builders still describe themselves as Tarion registered, which is outdated wording, so check the licence itself.
Before you sign, confirm these:
The builder appears in the HCRA's Ontario Builder Directory, searched by company name or licence number [11]
The licence covers both builder and vendor [11]
Tarion has confirmed enrolment for your home before the construction contract is signed [12]
The contract names the same licensed company
The builder carries liability insurance, and can show a WSIB clearance certificate [18]
These checks protect your warranty. Once a contract home is substantially complete, it carries one, two and seven year warranties against construction defects. Coverage reaches $400,000 and starts the day you take possession [12]. An owner-built home has no statutory warranty coverage [12].
One note on that last check. The WSIB exemption people quote says a clearance certificate isn't required. It's written for repairs or renovations arranged by a home's resident or occupant [18]. A new house on a vacant lot does not sit neatly inside that wording, and asking for the certificate costs you nothing either way.
Licensing tells you a builder can legally take on your home. Design-build decides how the work is run. At Building Dreams, planning, design, pricing, construction updates and warranty support sit with one accountable team [3]. The people who priced your development charges are the same people booking your framing inspection.
How Our Design-Build Process Works
In short: five phases, Discover through Handover. Development charges, permit timing and approvals are priced in Plan and Price, before any trade is booked [3].
Every custom home we build moves through the same five phases. Each one ends with something you can see and sign off on, so you always know what's decided and what comes next.
Phase | What happens | What you walk away with |
|---|---|---|
1. Discover | A first conversation and a site visit to talk through priorities, site conditions, budget and timing | A clear next step for your lot |
2. Design | Space planning, architectural coordination, 3D renderings and material selections | A design you can see before it's built |
3. Plan and Price | A detailed proposal covering labour, materials and allowances, then the contract, schedule, permits and procurement | A budget and schedule tied to your approval path |
4. Build and Communicate | Vetted trades, regular site reviews and daily BuilderTrend updates, with every change documented | Progress updates you can follow as the build moves |
5. Handover and Support | A detailed walkthrough, closeout documents and follow-up check-ins | Your home, its paperwork and ongoing support |
Phase 3 is where the numbers from earlier on this page come together. Development charges, permit timing and any variance or Escarpment approvals are priced and scheduled there, before a trade is booked [3].
Seeing the house early pays off later. A wall moved during framing costs time and money; the same wall moved on a rendering costs a conversation. That's why renderings and physical samples come before construction.
The best time to call is before drawings or major selections are final, while the design can still adjust to the lot [3].
Homes We've Built and Transformed Around Hamilton
In short: Project Gotham is a custom home in Ancaster, Project Crawford a custom home in the Greater Hamilton Area, and Project Inglewood a full interior and exterior renovation in Hamilton [13] [14] [15].
Our work includes custom homes in Hamilton and across the Greater Hamilton Area, along with full transformations of existing houses. Each project below opens to its full photo gallery.
Project Gotham: Custom Home, Ancaster
A transitional custom home with moody custom cabinetry, a marble slab fireplace and warm natural wood floors [13]. The lot sloped, so a large retaining wall now levels the backyard, making room for a pool and a private outdoor living space [13]. It's a good example of the sloped-lot planning covered earlier on this page.
Project Crawford: Custom Home, Greater Hamilton Area
A contemporary custom home built around wide rear glazing that opens onto the terrace [14]. Inside, a sculptural fireplace wall anchors the main floor, and spa-style marble bathrooms and custom millwork carry the detail upstairs [14].
Project Inglewood: Interior and Exterior Renovation, Hamilton
A full renovation of an existing Hamilton home, inside and out [15]. The kitchen was expanded into an open layout and the entry was reworked. Updates run through the house, while its original character stays in place [15].
Weighing a new build against transforming the house you have? Start your project and we'll talk through which path fits your lot and budget [4].
Warranty and Aftercare
In short: two layers. A two year builder materials and labour warranty [17], and, for homes enrolled with Tarion, statutory one, two and seven year coverage up to $400,000 from possession [12].
A new custom home in Ontario can carry two kinds of protection: the builder's own warranty and the provincial new home warranty backed by Tarion.
Builder warranty from Building Dreams | Ontario new home warranty (for homes enrolled with Tarion) | |
|---|---|---|
Backed by | Building Dreams Contracting Inc. [17] | The builder, backed by Tarion [12] |
Length | Two years [17] | One, two and seven year coverage, from the day you take possession [12] |
What it covers | Materials and labour on qualifying issues beyond normal wear and tear, under the written warranty terms [17] | Construction defects, up to $400,000 in total coverage [12] |
Protection works best when the handover is clear. Before you move in, we walk the home with you in detail. We note any outstanding items and explain the systems and finishes you'll live with [17]. After that, we check in as the house settles and stay reachable if questions come up [17].
Custom Home Builders in Hamilton: Questions and Answers
In short: the questions below cover cost, development charges, timelines, permits, variances, Escarpment approvals, builder licensing and warranty coverage.
What are development charges on a new house in Hamilton?
For the 2026 to 2027 rate year, the City of Hamilton's development charge on a new single detached home runs from $44,415 in the rural area to $102,451 in Urban Area A on the separated sewer system, before exemptions [1]. Education development charges add $3,579, and lots in Dundas or Waterdown carry a $1,931 special area charge [1].
When are development charges paid on a new home in Hamilton?
Education development charges are due before the building permit is issued. For a home you'll live in rather than rent, the City's own development charges are paid in one payment at occupancy [1]. The rate is usually set on the date the permit is issued, and it rises each June 1.
Does tearing down an old house lower development charges?
It can. If the old house came down under a demolition permit, a demolition credit reduces the development charges on the new home [1]. The credit applies to City and education charges, is available for up to five years after the demolition permit is issued, and is valued at the rate in effect when you rebuild.
How long does a building permit take in Hamilton?
Once an application is complete, the Ontario Building Code gives the chief building official 10 days to issue or refuse a permit for a house [5]. The clock doesn't start until the package is complete, and other required approvals, such as a conservation authority permit, need to be in place first.
When does a custom home need a minor variance?
You need one when your design sits close to, but outside, the zoning rules for your lot, such as a smaller setback or extra height. Hamilton's Committee of Adjustment decides, using four tests set by the Planning Act [6] [8]. After the decision, there's a 20 day appeal window.
Does my lot need Niagara Escarpment Commission approval?
Only if the lot sits inside the Niagara Escarpment Commission's Area of Development Control. There, a new house needs a development permit unless it's exempt, and the City's building permit can only follow it [9]. The Commission's online map shows whether a property falls inside that area.
What should I check before buying a lot in Hamilton?
Check what the zoning permits, how the lot is serviced and graded, and whether it sits in a conservation authority regulated area or the Niagara Escarpment Area of Development Control [7] [9]. Also check which development charge rate area it falls in, and whether a demolition credit applies [1].
How do I check that a custom home builder is licensed in Ontario?
Search the builder's company name or licence number in the Home Construction Regulatory Authority's Ontario Builder Directory [11]. A company that builds custom homes on land you own needs a licence as both builder and vendor. Builder licensing moved from Tarion to the HCRA on February 1, 2021.
What should a custom home contract include?
For a contract home, the builder must obtain enrolment confirmation from Tarion before entering the contract, and give you a Warranty Information Sheet covering your statutory warranty, the pre-delivery inspection and deposit protection [12]. Within 30 days of signing, the builder must send Tarion your contact details [12].
Is a custom home built on my own land covered by Tarion?
Yes, when a licensed builder builds it under contract and the home is enrolled with Tarion. Once the contract is substantially performed, the home is eligible for one, two and seven year warranties against construction defects, up to $400,000, starting on possession [12]. Homes owners build themselves have no statutory warranty.
Start Your Hamilton Custom Home
In short: bring the lot address, any survey or drawings, a budget range, your must-have rooms and a target move-in date to the first conversation.
Bring your lot to a custom home builder. Hamilton approvals, charges and site conditions are far easier to plan around before drawings are final.
Have these ready for the first conversation:
The lot address, or the listing if you haven't bought yet
Any survey, drawings or photos you already have
A rough budget range, including land if it's still to buy
The rooms and features you can't live without
When you'd like to move in
Start your project [4], call +1 289-903-0213, or visit us at K-85 Lancing Drive, Hamilton, ON L8W 2Z9.
Glossary
In short: plain definitions for the City, provincial and warranty terms used above.
Term | Meaning |
|---|---|
Applicable law | Other approvals, such as heritage, conservation authority or Niagara Escarpment permits, that must be in place before the City issues a building permit. |
Area of Development Control | Escarpment lands where a new house needs a Niagara Escarpment Commission development permit unless it's exempt. |
Contract home | A new home a licensed builder constructs under contract on land the owner already holds. |
Demolition credit | A reduction in development charges on a new home when an older building on the lot came down under a demolition permit within the past five years. |
Development charges | One-time City fees on new homes that help pay for growth, such as roads, water and wastewater systems. |
Minor variance | Permission from the Committee of Adjustment for a small departure from the zoning rules. |
Ontario Builder Directory | The HCRA's public listing of licensed new home builders and vendors. |
Statutory warranty | The new home warranty Ontario law provides on enrolled new homes, backed by Tarion. |
Additional dwelling unit | A secondary self-contained unit, such as an in-law suite or basement apartment, ancillary to a house. |
WSIB clearance certificate | A Workplace Safety and Insurance Board document showing a business account is in good standing [18]. |
Definition Bank
In short: the working vocabulary behind every figure above.
Term | Definition |
|---|---|
Applicable law | Other approvals, such as heritage, conservation authority or Niagara Escarpment permits, that must be in place before the City issues a building permit. |
Area of Development Control | Escarpment lands where a new house needs a Niagara Escarpment Commission development permit unless it's exempt. |
Contract home | A new home a licensed builder constructs under contract on land the owner already holds. |
Demolition credit | A reduction in development charges on a new home when an older building on the lot came down under a demolition permit within the past five years. |
Development charges | One-time City fees on new homes that help pay for growth, such as roads, water and wastewater systems. |
Minor variance | Permission from the Committee of Adjustment for a small departure from the zoning rules. |
Ontario Builder Directory | The HCRA's public listing of licensed new home builders and vendors. |
Statutory warranty | The new home warranty Ontario law provides on enrolled new homes, backed by Tarion. |
Additional dwelling unit | A secondary self-contained unit, such as an in-law suite or basement apartment, ancillary to a house. |
WSIB clearance certificate | A Workplace Safety and Insurance Board document showing a business account is in good standing [18]. |
Applicable law approval | Any outside approval, such as conservation or heritage, that must be settled before the City can issue a building permit [7]. |
Chief building official | The City official who decides whether a permit application is complete and issues or refuses the permit [5]. |
Committee of Adjustment | The City body that decides minor variance applications under the Planning Act [8]. |
Education development charges | School board charges on new homes, collected by the City and due before the permit is issued [1]. |
Ontario Land Tribunal | The provincial tribunal that hears appeals of Committee of Adjustment decisions [6]. |
Design-build | One accountable team carrying planning, design, pricing, construction and warranty support [3]. |
Allowance | A budget placeholder in the proposal for a selection not yet finalized [3]. |
Occupancy | The point at which you take possession; the City's development charges on a non-rental home are due then [1]. |
Entity Cards
In short: who decides what, and on which authority.
City of Hamilton Building Division
Property | Value |
|---|---|
Role | Issues building permits and runs inspections for new homes |
Decision window | 10 days on a complete house application, under the Ontario Building Code [5] |
Condition | All applicable law approvals must be in place before a permit issues [7] |
Fees | Building permit fee set per square metre of floor area [2] |
Development charges (City of Hamilton)
Property | Value |
|---|---|
What | One-time fees on new homes that help pay for growth infrastructure [1] |
Rate range | $44,415 rural to $102,451 Urban Area A separated sewer, single detached [1] |
Education charges | $3,579 per unit, all areas [1] |
When paid | City portion at occupancy for non-rental homes; education before permit [1] |
Exemptions | 20% to August 31, 2027; 4% to May 31, 2027 [1] |
Credit | Demolition credit for up to five years after the demolition permit [1] |
Committee of Adjustment
Property | Value |
|---|---|
Role | Decides minor variance applications under the Planning Act [6] [8] |
Tests | Minor, desirable, keeps intent of the Official Plan and the zoning by-law [6] |
After the decision | 20 day appeal window to the Ontario Land Tribunal [6] |
Who may appeal | Applicant, the Minister, specified persons and public bodies [6] |
Home Construction Regulatory Authority (HCRA)
Property | Value |
|---|---|
Role | Licenses new home builders and vendors in Ontario [11] |
Since | February 1, 2021, when registration moved from Tarion [11] |
Licence needed | Builder and vendor, for custom homes on land the owner holds [11] |
How to check | Ontario Builder Directory, by company name or licence number [11] |
Tarion
Property | Value |
|---|---|
Role | Administers Ontario's new home warranty program [11] [12] |
Contract home coverage | One, two and seven year warranties on construction defects [12] |
Maximum | Up to $400,000 in total coverage [12] |
Starts | On the day you take possession [12] |
Enrolment | Confirmed before the construction contract is signed [12] |
Not covered | Owner-built homes have no statutory warranty [12] |
Niagara Escarpment Commission
Property | Value |
|---|---|
Role | Issues development permits in the Area of Development Control [9] |
Requirement | A new house needs a development permit unless it is exempt [9] |
Order | The City's building permit can only follow the development permit [9] |
Zoning | The Niagara Escarpment Plan applies in place of City zoning there [10] |
Building Dreams Contracting Inc.
Property | Value |
|---|---|
Service | Design-build custom homes and whole-home transformations [3] |
Phases | Discover, Design, Plan and Price, Build and Communicate, Handover and Support [3] |
Communication | Daily BuilderTrend updates during construction [3] |
Builder warranty | Two year materials and labour warranty [17] |
Hamilton office | K-85 Lancing Drive, Hamilton, ON L8W 2Z9 |
HCRA licence | Pending client confirmation |
Sources
City of Hamilton. Development Charges Pamphlet, rates effective June 1, 2026 to May 31, 2027. https://www.hamilton.ca/sites/default/files/2026-05/development-charges-pamphlet-june1-2026-May31-2027.pdf
City of Hamilton. Building Permit Fees. https://www.hamilton.ca/build-invest-grow/construction-renovation/residential-building-renovation/building-permit-fees
Building Dreams Contracting Inc. Design-Build Process. https://www.buildingdreamsinc.ca/our-process
Building Dreams Contracting Inc. Start a Home Project. https://www.buildingdreamsinc.ca/contact
Government of Ontario. Building Code, O. Reg. 163/24, Division C, Article 1.3.1.3. https://www.ontario.ca/laws/regulation/r24163
Government of Ontario. Planning Act, R.S.O. 1990, c. P.13, s. 45. https://www.ontario.ca/laws/statute/90p13
City of Hamilton. Applicable Law for Building Permit Applications. https://www.hamilton.ca/build-invest-grow/construction-renovation/residential-building-renovation/applicable-law-building
City of Hamilton. Committee of Adjustment: Minor Variance. https://www.hamilton.ca/build-invest-grow/planning-development/committee-adjustment-delegated-consent-authority/minor
Niagara Escarpment Commission. Development Control Regulation 826/90 and 828/90. https://escarpment.org/permits/development-control-regulation-826-90-and-828-90/
City of Hamilton. Pleasantview Area Land Use Study. https://www.hamilton.ca/build-invest-grow/planning-development/planning-design-studies/pleasantview-area-land-use-study
Home Construction Regulatory Authority. Do I Need a Licence?; Licensing Fees and Conduct Guidelines Posted. https://www.hcraontario.ca/do-i-need-a-licence/ ; https://www.hcraontario.ca/news/news-release-licensing-fees-and-conduct-guidelines-posted/
Tarion. Contract Homes; Building and Selling Contract Homes. https://www.tarion.com/node/66068 ; https://www.tarion.com/builders/building-selling-contract-homes
Building Dreams Contracting Inc. Project Gotham. https://www.buildingdreamsinc.ca/project-gotham
Building Dreams Contracting Inc. Project Crawford. https://www.buildingdreamsinc.ca/project-crawford
Building Dreams Contracting Inc. Project Inglewood. https://www.buildingdreamsinc.ca/project-inglewood
Google Business Profile, Building Dreams Contracting Inc. URL pending from client
Building Dreams Contracting Inc. Home Warranty and Aftercare. https://www.buildingdreamsinc.ca/our-warranty
Workplace Safety and Insurance Board. Questions and answers: Clearances. https://www.wsib.ca/en/clearancefaqs
All sources accessed October 13, 2026.
