Kitchen with two white oak islands and glass pendants in a Building Dreams home

Soft Costs and Development Charges: The Budget Lines Most Custom Home Owners Miss

November 23, 2026•21 min read

Updated November 11, 2026

A builder's price per square foot covers the house itself. That means the foundation, framing, roof, mechanical systems and finishes. It doesn't cover the fees, charges and taxes that come with putting a new home on a lot in Hamilton, Burlington or Niagara. Those are soft costs. On a custom home in Ontario, they need their own lines in the budget.

A quote tells you what the house costs. A custom home budget tells you what it costs to move in. Most of the gap can be priced before you sign. Each line below shows the public source behind it and the date it was checked. For what the house itself costs per square foot, see the Ontario custom home cost guide.

Direct Answer

Soft costs on a custom home in Ontario are the costs outside construction itself: design and engineering, surveys, permits, development charges, utility connections, HST, contingency and financing. On a lot you own, enhanced HST relief of up to $130,000 applies only if construction starts between April 1, 2026 and March 31, 2027 [1].

TL;DR

  • A per square foot quote prices the house. Design, surveys, permits, development charges, hookups, HST, contingency and financing sit on top.

  • On your own lot, the CRA treats the home as owner-built, and the enhanced HST relief depends on construction starting by March 31, 2027 [1].

  • Ontario has announced the standard $24,000 rebate also ends for owner-built homes started after that date [5].

  • Hamilton's City charge on a detached house runs $44,415 to $102,451 before temporary exemptions; its planned elimination isn't in effect yet [9][10].

  • Most development charges are now due at occupancy, but school board charges are due before the permit [9][16].

  • On a $1,000,000 Hamilton build, the soft cost layer runs about $157,000 to $395,000 before financing.

One liner: Price every soft cost line by address and start date before you sign.

Key Numbers

Stat

What it measures

Source

13%

HST on new construction

CRA [1]

$130,000

Maximum owner-built HST relief

CRA Notice 346, August 2026 [1]

March 31, 2027

Owner-built start deadline

CRA Notice 346 [1]

$44,415 to $102,451

Hamilton City charge, detached

City of Hamilton, June 2026 [9]

$3,579

Hamilton school board charges

City of Hamilton, July 2026 [9]

$12,021.25

Halton school board charges

Town of Oakville, June 2026 [12]

$32,129

Niagara Region charge, urban

Niagara Region, 2026 [14]

$18.32 per m²

Hamilton permit fee

City of Hamilton, November 2026 [4]

$8,000 to $25,000 and up

Architectural drawings

Green Building Canada, June 2026 [2]

5% to 10% of hard costs

Contingency

CMHC, Q1 2025 [23]

10%

Construction holdback

Construction Act s. 22 [25]

What Counts as a Soft Cost on an Ontario Custom Home

In short: Soft costs are what you pay to design, approve, connect and finance the house, rather than to build it.

A soft cost is any cost that doesn't go into the structure itself. Hard costs are the labour and materials you can see on site. Soft costs are the drawings, approvals, fees and taxes that let that work happen. One detail catches people out. Soft costs don't shrink much when you simplify the floor plan, because a smaller house still needs drawings, a survey, a permit and a water connection.

Soft cost line

What it covers

Published figure

Source

Design and drawings

Architectural drawings and the permit set

$8,000 to $25,000 and up

Green Building Canada, June 2026 [2]

Engineering

Structural and other engineering reports

$5,000 to $20,000

Green Building Canada, June 2026 [2]

Survey

Updated Surveyor's Real Property Report in the GTA

$2,500 to $3,500, with staking extra

RE/MAX Canada, August 2026 [3]

Building permit

Plan review and inspections

$18.32 per square metre in Hamilton

City of Hamilton, November 2026 [4]

Development charges

City, region and school board growth charges

Set by by-law for each address

Detailed below

Utility connections

Water, sewer, hydro and gas hookups

$5,000 to $30,000; Hamilton water and sewer service permits $187 each

Green Building Canada [2]; City of Hamilton [4]

HST

13% on construction

Relief depends on the construction start date

Canada Revenue Agency [1]

Contingency and financing

A reserve for changes, plus loan interest during the build

Set for each project

Detailed below

Soft costs custom home Ontario: lines and published figures at the time of writing.

Land, plus the legal fees to buy it and register the construction mortgage, sits in its own lines outside this list.

Some of these lines can sit inside a builder's contract and some never do. In a design-build agreement, design and engineering can be priced in the same contract as construction. Development charges, permit fees and HST are set by governments, so no builder can discount them. Ask for every line by name when you compare quotes. That way custom home soft costs in Ontario don't get counted twice or left out.

HST on a New Custom Home in Ontario: The Construction Start Date Decides the Rebate

In short: On your own lot, the enhanced HST relief depends on when construction starts. A start after March 31, 2027 loses it.

If you own the lot and hire a builder, the Canada Revenue Agency (CRA) treats the house as owner-built [1]. For an owner-built home, the enhanced relief turns on the date construction begins, not the date you sign a contract. Construction has to begin between April 1, 2026 and March 31, 2027, and the house has to be substantially complete before 2030 [1].

The amounts are large. On $900,000 of construction, 13% HST comes to $117,000. Inside the window, two payments can cover most or all of it:

  • Provincial part (8%). The Ontario enhanced new housing rebate, together with the existing Ontario rebate, pays up to $80,000. That's the full 8% on a home valued up to $1 million, a flat $80,000 up to $1.5 million, and a partial amount below $1.85 million [1].

  • Federal part (5%). The Ontario New Home Affordability Payment (ONHAP) pays up to $50,000, less any federal rebate you're entitled to [1].

The value test applies when the house is substantially complete, and for an owner-built home the CRA counts the land in that value [7]. A valuable lot can narrow the relief even when construction costs stay the same.

Date test

Built on land you own

Bought from a builder

Agreement signed

Not the test

April 1, 2026 to March 31, 2027

Construction begins

April 1, 2026 to March 31, 2027

On or before December 31, 2028

Substantially completed

Before 2030

On or before December 31, 2031

Value limit

Under $1,850,000 at substantial completion

Total price under $1,850,000

How it's claimed

Form GST191 with Form RC7191-ON, filed with the CRA

Usually credited by the builder at closing

HST on new custom home Ontario: date tests from CRA Notice 346, August 2026 [1].

What Changes After March 31, 2027

Ontario has announced that the standard Ontario New Housing Rebate, worth up to $24,000, ends for transactions that begin on or after April 1, 2027. For owner-built homes, it stays available only where construction begins by March 31, 2027 [5]. A later start loses both the enhanced relief and the $24,000 fallback that many cost guides still quote. First-time buyers keep one route: the federal First-Time Home Buyers' (FTHB) GST/HST rebate covers owner-built homes started on or after March 20, 2025, up to $50,000 [6].

When does construction begin? For the purpose-built rental rebate, the CRA has said construction generally begins when excavation work starts [8]. That's a sensible planning test here too. Drawings, permits and financing all have to be ready before excavation, which is why the design and permit stages in the Building Dreams process come first. If your start will fall after March 31, 2027, budget the full 13% HST on construction. If it might land inside the window, price the budget both ways.

Development Charges on a New Home in Hamilton, Halton and Niagara

In short: The same house can carry different charges depending on the city, the date of the permit and the school board.

Development charges are one-time fees that a city, a region and the school boards put on a new home to help pay for roads, water, sewers and other growth services. Each sets its own rate by by-law, and most rates change every year. Budget them by address, using the rates for the date you expect to pull the permit.

Market

Who charges

Single-detached charge, 2026

When it's paid

Hamilton

City of Hamilton

$44,415 rural to $102,451 urban, before the temporary 20% and 4% exemptions [9]

At occupancy [9]

Hamilton

Hamilton-Wentworth public and Catholic school boards

$3,579 combined [9]

Before the building permit [9]

Burlington (Halton)

Halton Region

$41,368.50 for roads and services, plus $38,512.17 for water and wastewater in Greenfield areas [11]

At occupancy [11]

Burlington (Halton)

Front-ending Recovery Payment, where it applies

$9,500 [11]

At the building permit [11]

Burlington (Halton)

Halton public and Catholic school boards

$12,021.25 combined [12]

Before the building permit [12]

Burlington (Halton)

City of Burlington

$20,595 base rate, indexed each April [13]

At occupancy [16]

Niagara-on-the-Lake

Niagara Region and the Town

$32,129 Region plus $17,178 Town, urban [14][15]

Set by the Region and Town

Rates in effect for 2026. Development charges new home Halton figures use Halton Region's April 1, 2026 rates. Hamilton school board rates apply from July 1, 2026, and Halton school board rates from June 1, 2026.

Hamilton is the market to watch. The City has committed to eliminating residential development charges from March 30, 2026 to March 31, 2029. As of its August 26, 2026 update, that isn't in effect yet. Owners keep paying through the current process until a provincial agreement is signed, then get refunds back to March 30, 2026 [10]. City policy doesn't change the school board charges [9]. If you're planning a custom home in Hamilton, budget the City charge at today's rates and treat any refund as a bonus.

For development charges on a new home in Halton, the lot type matters as much as the city. Built Boundary lots pay a lower water and wastewater charge, and teardowns can earn credits. The Burlington and Oakville cost guide walks through both. In Niagara, the Region and Town charges for an urban lot in Niagara-on-the-Lake come to about $49,300 before any school board charge. That's about half of Hamilton's top urban rate.

Timing has moved too. Since the 2025 changes to the Development Charges Act, charges on a home you'll live in are generally due at occupancy rather than at permit [16]. School board charges still come due before the permit is issued.

Design, Engineering and Survey Fees

In short: These are the first soft costs you pay, and they decide how smoothly the permit goes.

Permit drawings for a new house have to come from an architect, an engineer or a designer qualified under the Ontario Building Code with a Building Code Identification Number (BCIN). The one exception is an owner who designs the house themselves [17]. Published ranges put architectural drawings at $8,000 to $25,000 and up, and engineering reports at $5,000 to $20,000 [2].

The survey is easy to underestimate. The one you bought the lot with may be years old. Construction staking and foundation layout are also priced separately from the survey itself [3]. Get the survey and a soil report before design starts, as covered in checking a lot before you build.

Where these fees sit depends on how you hire. In the Building Dreams process, design covers space planning, architectural coordination, 3D renderings and material selections, and a plan and price stage then sets out labour, materials and allowances. The trade-offs are laid out in design-build vs. separate contracts. Money spent on complete drawings is money you don't spend on redesign while a permit sits in review.

Building Permits and Approvals

In short: The permit fee itself is modest next to development charges, but several smaller fees and a deposit come due at the same counter.

Each municipality sets its own building permit fees. Hamilton and Niagara-on-the-Lake charge by the floor area of the new house, and each schedule defines which areas count, so check that definition against your drawings.

Market

Building permit fee, new detached house

Other fees and deposits at permit

Hamilton

$18.32 per square metre [4]

$453 foundation permit; $291 minimum fee [4]

Burlington

Set by the City's Building Permit By-law 30-2026 [20]

$2,110 zoning clearance certificate per new house [18]

Niagara-on-the-Lake

$2.16 per square foot [19]

$4,500 lot grading, damage and road cleaning deposit, refundable when the file closes [19]

2026 fee schedules. Hamilton's planning committee will consider a 3% fee increase on December 1, 2026 [4].

A quick check on a 3,000 square foot house: that's about 279 square metres, or roughly $5,100 in Hamilton permit fees. The same floor area comes to $6,480 in Niagara-on-the-Lake, before the deposit. Neither figure is large on its own. Together with the zoning, grading and service permits, though, the permit counter adds a few thousand dollars that sit outside a per square foot quote.

Lots near creeks, wetlands or the lake can need a conservation authority permit before the building permit. In Halton, a formal letter confirming whether a property is regulated costs $360 [26].

Timelines and what triggers a permit are covered in what to expect from permits.

Utility Connections and Servicing

In short: The municipal hookup fees are small. The trench, the pipe and, on rural lots, a well and septic system are where the money goes.

Every new house needs water, sewer or septic, power and usually gas. The municipality charges a modest fee to permit and inspect the connection. The larger cost is the contractor's work to dig, lay pipe and restore the ground between the house and the street.

Cost

Hamilton

Burlington (Halton)

Rural lot

Municipal water and sewer fees

$187 each for water and sewer service, or $168 each with a complete building permit application [4]

Water: $238 permit, $496.96 tap, $536 inspection, $409.44 or $515.03 meter [21]

Not connected to municipal services

On-site systems

None on serviced lots

None on serviced lots

Well drilling $10,000 to $25,000; septic $15,000 to $40,000 [2]

Contractor's trench and pipe work

Priced by site

Priced by site

Priced by site

Published range for all utility hookups: $5,000 to $30,000 [2]. Municipal fees from 2026 schedules.

Power follows its own steps. You apply to the local electricity distributor for a new service, and the Electrical Safety Authority (ESA) inspects the site and authorizes the connection before the final hookup [22]. Builders often request temporary power for construction in the same process [22].

Distance to the street, sewer depth and soil conditions drive most of the contractor's price. A current survey and a soil report give the first read on all three.

Contingency and Financing

In short: Hold a reserve for changes and site unknowns, and plan for loan interest and the 10% holdback while the house goes up.

A contingency is money you set aside and hope not to spend. It covers the changes you decide on mid-build and the conditions nobody can see until the ground is open. CMHC's Ontario cost estimates advise holding 5% to 10% of hard costs [23]. Those estimates were priced for suites and small multi-unit buildings rather than custom detached homes, so set your own figure against the design and the lot. On $1,000,000 of construction, 10% is $100,000 kept aside.

Financing is a soft cost too. A construction loan pays out in stages, called progress advances, as work is completed and checked [24]. Interest runs on what has been drawn, so the bill grows as the house does. Budget for that interest, plus somewhere to live if you're replacing the house you're in.

The holdback affects cash flow rather than the total. Under Ontario's Construction Act, each payer on a construction contract keeps back 10% of the price of services and materials as they're supplied [25]. That money is still owed and is released on a schedule the Act sets, so plan for it in the draw schedule rather than treating it as savings.

Sample Custom Home Budget in Ontario: Soft Cost Lines

In short: On a $1,000,000 build in Hamilton, the soft cost layer runs from about $157,000 to $395,000, and the HST start date accounts for $130,000 of that spread.

Soft cost line

Construction starts after March 31, 2027

Construction starts by March 31, 2027

Design and drawings [2]

$8,000 to $25,000

$8,000 to $25,000

Engineering [2]

$5,000 to $20,000

$5,000 to $20,000

Survey, GTA benchmark [3]

$2,500 to $3,500

$2,500 to $3,500

Building permit, 278.7 m² at $18.32 [4]

About $5,100

About $5,100

Water and sewer service permits [4]

$336 to $374

$336 to $374

Utility hookup work [2]

$5,000 to $30,000

$5,000 to $30,000

City development charge, after the 20% and 4% exemptions [9]

$77,863

$77,863

School board charges [9]

$3,579

$3,579

HST on $1,000,000 of construction [1][5]

$130,000

As low as $0 if the home's value qualifies

Contingency at 5% to 10% [23]

$50,000 to $100,000

$50,000 to $100,000

Financing interest

Depends on rate and draws

Depends on rate and draws

Total before financing

About $287,400 to $395,400

About $157,400 to $265,400

Custom home budget Ontario example: a 3,000 sq ft detached house on a serviced urban lot in Hamilton (separated sewer, Area A), $1,000,000 of construction, built on land the owner holds. Published figures at the time of writing, not a quote.

Two lines could still move. If Hamilton's development charge elimination takes effect, the City charge would be refunded back to March 30, 2026 [10]. First-time buyers who start after the window can still recover up to $50,000 of the federal part through the FTHB rebate [6].

How to Price Soft Costs Before You Sign

In short: Five checks turn soft costs from surprises into budget lines.

  1. Get the development charges for your address, school boards included, at the rates for your expected permit date.

  2. Set your construction start date against March 31, 2027, and price HST both ways.

  3. Order a current survey and a soil report before design starts.

  4. Ask every quote to list design, engineering, permits and hookups as separate lines.

  5. Set a contingency figure and a draw schedule that allows for the 10% holdback.

In the Building Dreams process, pricing follows design, with labour, materials and allowances set out before the contract is final. Start a home project to talk through your lot and these lines.

Frequently Asked Questions

In short: Quick answers on soft costs, HST, development charges, permits and contingency.

What are soft costs on a custom home in Ontario?

Soft costs are what you pay to design, approve, connect and finance a custom home, rather than to build it. They include design and engineering, surveys, permits, development charges, utility connections, HST and a contingency.

How much are soft costs on a custom home in Ontario?

In a worked Hamilton example with $1,000,000 of construction, the soft cost lines total about $157,000 to $395,000 before financing. HST alone moves the total by $130,000, depending on when construction starts.

Is there HST on a new custom home in Ontario?

Yes. New construction carries 13% HST. On land you own, enhanced relief of up to $80,000 on the provincial part and up to $50,000 on the federal part applies if construction starts between April 1, 2026 and March 31, 2027 [1].

Does signing a contract before March 31, 2027 lock in the HST relief for a custom home?

No. For a home built on land you own, the test is when construction begins, not when you sign [1]. A builder-purchase agreement follows a different rule.

What happens to the $24,000 Ontario HST rebate after March 31, 2027?

Ontario has announced it ends for transactions beginning on or after April 1, 2027. Owner-built homes keep it only where construction begins by March 31, 2027 [5].

What are development charges on a new home in Halton?

In Burlington, Halton Region charges $41,368.50 for roads and services plus $38,512.17 for water and wastewater in Greenfield areas. The school boards add $12,021.25, the City of Burlington adds its own charge, and a $9,500 Front-ending Recovery Payment applies on some lots [11][12][13].

Are Hamilton development charges waived?

Not yet. Hamilton has committed to eliminating residential charges from March 30, 2026 to March 31, 2029, but as of its August 26, 2026 update, owners keep paying until a provincial agreement is signed, with refunds back to March 30, 2026 [10].

When are development charges paid on a new home in Ontario?

For a home you'll live in, municipal and regional charges are generally paid at occupancy after the 2025 changes to the Development Charges Act [16]. School board charges are still due before the building permit [9].

How much is a building permit for a new house in Hamilton?

Hamilton charges $18.32 per square metre for a detached house, so a 3,000 sq ft home comes to about $5,100 [4]. Water and sewer service permits add $187 each.

How much contingency should I budget for a custom home?

CMHC's Ontario cost estimates advise 5% to 10% of hard costs [23]. On $1,000,000 of construction, that's $50,000 to $100,000.

What should a custom home budget in Ontario include?

Land, construction, and every soft cost line: design, engineering, survey, permits, development charges, utility connections, HST, contingency and financing interest. Price each line by address and expected start date.

Definition Bank

Term

Meaning

Soft costs

Costs to design, approve, connect and finance a house, outside labour and materials [2]

Hard costs

Labour and materials that go into the structure [2]

Owner-built home

A home on land you own that you build or hire someone to build, for HST rebate purposes [1]

Ontario Enhanced New Housing Rebate

Temporary relief of up to $80,000 on the 8% provincial part of HST [1]

Ontario New Home Affordability Payment (ONHAP)

Up to $50,000 covering the 5% federal part of HST [1]

Development charge

A one-time fee on a new home to help pay for growth services such as roads and water [9]

Education development charge

The school boards' charge on a new home, due before the building permit [9]

Front-ending Recovery Payment

A $9,500 Halton payment on some urban lots, collected at permit [11]

BCIN

Building Code Identification Number, held by designers qualified under the Ontario Building Code [17]

Holdback

The 10% of each payment kept back under Ontario's Construction Act [25]

Progress advance

A stage payment from a construction loan as work is completed [24]

Quick Facts

Owner-built HST relief (CRA Notice 346)

Property

Value

Construction start window

April 1, 2026 to March 31, 2027 [1]

Substantial completion

Before 2030 [1]

Value limit

Under $1,850,000 at substantial completion [1]

Maximum relief

$80,000 provincial plus $50,000 ONHAP [1]

Forms

GST191 with RC7191-ON [1]

City of Hamilton development charges, 2026

Property

Value

Single-detached, City

$44,415 to $102,451 [9]

Temporary exemptions

20% and 4% [9]

School boards

$3,579 [9]

Elimination

Committed March 30, 2026 to March 31, 2029, not yet in effect [10]

Halton Region charges, Burlington, 2026

Property

Value

Roads and services

$41,368.50 [11]

Water and wastewater, Greenfield

$38,512.17 [11]

Front-ending Recovery Payment

$9,500 where it applies [11]

School boards

$12,021.25 [12]

Niagara-on-the-Lake charges, 2026

Property

Value

Niagara Region, urban

$32,129 [14]

Town, urban

$17,178 [15]

Permit fee

$2.16 per sq ft [19]

Lot grading deposit

$4,500, refundable [19]

Sources

  1. Canada Revenue Agency. GST/HST Notice 346, Ontario Enhanced New Housing Rebate. August 2026 version. https://www.canada.ca/en/revenue-agency/services/forms-publications/publications/notice346/ontario-enhanced-new-housing-rebate.html

  2. Green Building Canada. Average Cost to Build a House in Ontario in 2026. June 22, 2026. https://greenbuildingcanada.ca/cost-build-house-ontario/

  3. RE/MAX Canada. What Is a Property Survey and Do You Need One? August 24, 2026. https://blog.remax.ca/what-is-a-property-survey-and-do-you-need-one/

  4. City of Hamilton. Building Permit Fees. Modified November 10, 2026. https://www.hamilton.ca/build-invest-grow/construction-renovation/residential-building-renovation/building-permit-fees

  5. Government of Ontario. 2026 Fall Statement, Annex: Details of Tax Measures and Other Legislative Initiatives. October 29, 2026. https://budget.ontario.ca/2026/fallstatement/annex.html

  6. Canada Revenue Agency. First-time buyers can save more on new homes: the FTHB GST/HST rebate is available now. March 17, 2026. https://www.canada.ca/en/revenue-agency/news/newsroom/tax-tips/tax-tips-2026/first-time-buyers-can-save-more-on-new-homes-the-first-time-home-buyers-gst-hst-rebate-is-available-now.html

  7. Canada Revenue Agency. GST/HST Memorandum 19.3.4, Rebate for Owner-Built Homes. https://www.canada.ca/en/revenue-agency/services/forms-publications/publications/19-3-4/rebate-owner-built-homes.html

  8. Canada Revenue Agency. GST/HST Notice 336, Purpose-built Rental Housing Rebate. June 2024. https://www.canada.ca/en/revenue-agency/services/forms-publications/publications/notice336/purpose-built-rental-housing-rebate.html

  9. City of Hamilton. Development Charges Pamphlet, rates effective June 1, 2026 through May 31, 2027. https://www.hamilton.ca/sites/default/files/2026-07/development-charges-pamphlet-june1-2026-May31-2027.pdf

  10. City of Hamilton. Development Charge Reduction Program (DCRP) Application Update. August 26, 2026. https://www.hamilton.ca/sites/default/files/2026-08/comms-update-development-charge-reduction-program-DCRP-Application-Update-City%20Wide.pdf

  11. Halton Region. Development Charges and Front-ending Recovery Payment. 2026 rates. https://www.halton.ca/the-region/finance-and-transparency/financing-growth/development-charges-front-ending-recovery-payment

  12. Town of Oakville. Development Charges (Halton school board rates as of June 1, 2026). https://www.oakville.ca/town-hall/budget-finances/growth-infrastructure-financing-tools/development-charges/

  13. City of Burlington. By-law 41-2024, Development Charges. https://www.burlington.ca/en/by-laws-and-animal-services/resources/By-laws/By-law-Search/2024-By-laws/041-2024-By-law.pdf

  14. Niagara Region. Current Fees for Development Charges. 2026. https://www.niagararegion.ca/business/property/current-fees.aspx

  15. Town of Niagara-on-the-Lake. Development Charges, January 1 to December 31, 2026. https://www.notl.com/sites/default/files/2026-02/Development%20Charges%20-%20January%201%2C%202026.pdf

  16. Government of Ontario. Development Charges Act, 1997, S.O. 1997, c. 27. https://www.ontario.ca/laws/statute/97d27

  17. Town of Newmarket. Building and Renovating (designer qualifications under the Ontario Building Code). https://forms.newmarket.ca/LivingHere/Pages/Building-and-Renovating.aspx

  18. City of Burlington. 2026 Zoning Fees. Effective January 1, 2026. https://www.burlington.ca/en/planning-and-development/resources/Zoning-Clearance-Certificates/2026-Zoning-Fees.pdf

  19. Town of Niagara-on-the-Lake. 2026 Building User Fees and Service Charges. https://www.notl.com/sites/default/files/2026-04/2026%20Building%20Fees.pdf

  20. City of Burlington. By-law 30-2026, Building Permit By-law. https://www.burlington.ca/en/by-laws-and-animal-services/resources/By-laws/By-law-Search/2026-By-laws/030-2026---New-Building-Permit-By-law.pdf

  21. Halton Region. By-law 48-25, 2026 Water Fees. https://www.halton.ca/getmedia/700ba3e7-7c73-4749-8e9e-5321d572238b/fn-by-law-48-25-2026-water-fees-jan-2026.pdf

  22. Alectra Utilities. Make a Service Request. https://alectrautilities.com/make-service-request

  23. CMHC. Housing Design Catalogue Construction Cost Estimate Summary, Ontario. Q1 2025 estimates. https://assets.cmhc-schl.gc.ca/sites/housing%20catalog/resources/hdc-construction-cost-estimate--summary-ontario-en.pdf

  24. CMHC. CMHC Improvement: new construction financing. https://www.cmhc-schl.gc.ca/professionals/project-funding-and-mortgage-financing/mortgage-loan-insurance/mortgage-loan-insurance-homeownership-programs/cmhc-improvement

  25. Government of Ontario. Construction Act, R.S.O. 1990, c. C.30, s. 22. https://www.ontario.ca/laws/statute/90c30

  26. Conservation Halton. Property Inquiries. https://www.conservationhalton.ca/property-inquiries/

Building Dreams Inc.
Building Dreams Inc. is a custom home builder and design-build renovation team serving Hamilton, Burlington, Oakville, and the GHA. Guided by clear communication, detailed planning, and honest craftsmanship, the BDC team turns complex home transformations into structured, stress-free projects built around the way families actually live.