Planning a Spring 2027 Custom Home Build? What to Decide This Winter
Updated November 11, 2026
Most people picture a custom home starting with an excavator. On paper, it starts months earlier, with a survey, a set of drawings and a permit file. If you want to break ground in spring 2027, the answer to when to start planning a custom home build is short: this December. The decisions below are the ones that can't wait for the snow to melt.
Direct Answer
Start planning a custom home build in December for a spring 2027 groundbreaking. In Ontario, a complete house permit application gets a decision within 10 business days in any season, but that clock starts only after approvals like a minor variance or conservation authority permit are in hand [1][2]. Winter is for that work.
TL;DR
Start in December 2026 for a spring 2027 groundbreaking.
Ontario's 10-business-day permit review for a house starts only once the application is complete, whatever the season.
Minor variances, conservation authority permits and Burlington's Pre-Building Approval come before the building permit.
Tree permits and removals belong in winter, before nesting season, which can start in mid-March.
Lock the footprint, height, foundation, windows and mechanical system before permit drawings are filed. Finishes can be allowances.
The builder enrols the home with Tarion before the contract, and municipal and regional development charges are now paid before occupancy.
Spring thaw load limits run March 1 to April 30, so many lots start digging in late April or May.
One liner: Build the permit file in winter so it's complete when the ground is ready.
Key Numbers
Stat | What it measures | Source |
|---|---|---|
10 business days | House permit decision, complete application | Government of Ontario [1] |
21 days | Conservation authority completeness check | Government of Ontario [2] |
90 days | Conservation authority decision | Government of Ontario [2] |
Within 30 days | Minor variance hearing | Planning Act s. 45(4) [7] |
20 days | Minor variance appeal period | Planning Act s. 45(12) [7] |
$2,110 (2026) | Burlington zoning review fee, new home | City of Burlington [9] |
$1,645 (2026) | Burlington grading review fee, new home | City of Burlington [9] |
$505 | Hamilton Applicable Law Review | City of Hamilton [14] |
90% (since November 21, 2025) | Deemed minimum setback | O. Reg. 545/06 [12] |
20 cm diameter | Burlington private tree permit threshold | City of Burlington [17] |
Mid-March | Earliest general nesting start | Environment and Climate Change Canada [3] |
March 1 to April 30 | Spring reduced load period | City of Hamilton [4] |
5,000 kg | Reduced load axle limit | Highway Traffic Act s. 122 [35] |
5 business days | Locate request notice | Ontario One Call [36] |
Since November 3, 2025 | Development charges deferred to occupancy | OBOA [28] |
When to Start Planning a Custom Home Build for Spring 2027
In short: Start in December. The approvals a lot may need run on fixed legal clocks, and they have to finish before the permit clock begins.
Month | What to decide | Why it can't wait |
|---|---|---|
December 2026 | Confirm zoning, order a survey, check for conservation authority limits and protected trees, choose your design-build team | Every later step depends on what the lot allows |
January 2027 | Settle the floor plan, footprint and height; apply for any conservation authority permit and tree permit | A conservation authority has up to 21 days to confirm a file is complete and 90 days to decide [2] |
February 2027 | Finish permit drawings, the grading plan and the selections that change them; remove approved trees | Nesting can begin as early as mid-March [3] |
March 2027 | Sign the construction contract and submit a complete building permit application | A complete house application gets a decision within 10 business days [1] |
April 2027 | Book excavation and deliveries for after the spring load period | Reduced load limits run March 1 to April 30 on posted roads [4] |
A custom home build timeline has two halves: the paperwork and the build. The build gets the attention, but the paperwork sets the start date.
Here's a quick example. Say your lot backs onto a creek and needs a conservation authority permit. The authority has 21 days to confirm the application is complete, then 90 days to decide [2]. That's up to 111 days, close to four months, before the building permit application can be complete. File in early January, and the decision could land in late April. Add the 10 business days the Ontario Building Code allows for the building permit itself [1], and a May start is realistic.
Spring brings two more limits to plan around. Ontario's spring thaw load restrictions apply on posted roads [4], which affects concrete trucks and excavation equipment. And migratory birds can start nesting as early as mid-March [3], which makes tree clearing harder once the weather turns.
Most of the winter planning custom home owners do happens at a desk, not on site. In a design-build process, design, pricing and permits move together, so each piece is ready when the next one needs it.
Permit Submissions: Why the Clock Starts at "Complete"
In short: The 10-day permit review doesn't change with the seasons. What changes is how much of the approval work is finished before the application goes in.
You'll often hear that permits move faster in winter because fewer people apply. In Ontario, a complete application for a house gets a decision within 10 business days in any season, and that clock only starts once the application is complete [1].
So the real question is what "complete" means, and how long it takes to get there.
What Makes an Application Complete
A complete application has the right forms, drawings and fees. It also has to clear applicable law: other rules, such as zoning and conservation authority permits, that generally must be met before a building permit is issued [1]. In Hamilton, applicable law approvals have to be in hand before a permit application can be accepted or issued [5], and a permit is issued only if the house meets the zoning by-law for the lot [6].
Approvals That Come First
Approval | Legal clock | Needed when |
|---|---|---|
Minor variance | Hearing within 30 days of the application; final after a 20-day appeal period [7] | The design breaks a zoning rule |
Conservation authority permit | 21 days to confirm the file is complete, 90 days to decide [2] | The lot is in a conservation authority regulated area |
Burlington Pre-Building Approval | Zoning, grading and forestry reviewed in one application [8] | A new detached home in Burlington |
Building permit | 10 business days once complete [1] | Every new home |
Picture two applications filed in March. One goes in while a minor variance still waits for its hearing. The other goes in after the variance became final in February. The second starts its 10-day review right away. The first can wait about seven weeks on the legal clocks alone before its review even begins [7].
Hamilton, Burlington and Niagara Offices
Each city runs its own permit office, and the first step differs. In Burlington, a new detached home starts with a Pre-Building Approval application that bundles zoning, grading and drainage, and forestry reviews [8]. For 2026, the zoning review fee is $2,110 per unit and the grading review is $1,645 [9]. Hamilton requires a professional grading plan with the permit application for an infill home [6].
In Niagara, each local municipality issues its own building permits. Niagara Falls asks applicants to finish approvals from other agencies before applying, and its review times apply only to complete applications that meet zoning and applicable law [10]. Its applicable law checklist includes Niagara Peninsula Conservation Authority permits for wetlands, shorelines and watercourses [11].
That's the work winter is good for. Settle the variance, the conservation authority permit and the drawings first, and the application is complete the day it goes in. For fees and the permits renovations need, see renovation and custom home permits.
Lot Checks to Finish This Winter
In short: Confirm what the lot allows before design goes far: zoning, conservation authority limits, grading, services, soil and trees.
A lot can look ready from the street and still carry rules that reshape the house. These checks belong in December and January, while the design is still a sketch. For a fuller list, see lot checks before you build.
Zoning and Setbacks
Start with the zoning by-law for your lot: setbacks, height and lot coverage. Since November 21, 2025, Ontario treats a minimum setback as 90% of the by-law figure on qualifying urban residential land [7][12]. On those lots, a 1.2 m side yard works out to 1.08 m. The rule doesn't apply within 300 m of an active railway, or within 120 m of a wetland, Great Lakes shoreline, inland lake or river valley [13]. In Hamilton, a Zoning Compliance Review confirms which rules apply before you apply for a permit, and the Applicable Law Review costs $505 [14].
Conservation Authority and Grading
If the lot is near a creek, wetland or shoreline, check whether it sits in a conservation authority regulated area, and apply through that local authority [2]. Hamilton, Burlington and Niagara lots can fall under different authorities. A topographic survey feeds the grading plan, which Hamilton requires with the permit application for an infill home [6].
Services and Soil
Confirm how the house will connect to water, sewer or septic, and hydro, and order a soil (geotechnical) report if your engineer asks for one. Both shape the foundation design, so they need answers before the drawings are final.
Trees and the Nesting Season
Tree rules vary by city. Hamilton has no city-wide private tree by-law, but older by-laws still apply in Ancaster and Dundas [15], and a harmonized by-law is in draft [16]. Burlington requires a permit to injure or remove a private tree 20 cm in diameter or larger in its urban area [17], and its Pre-Building Approval includes a forestry review [8]. In Niagara, Fort Erie's tree by-law covers private land inside the Town's urban boundary [18].
Timing matters too. Occupied migratory bird nests are protected, and federal guidance says to avoid clearing vegetation during the nesting period [19], which can start as early as mid-March [3]. Sort out tree permits in January, and approved removals can happen before then.
Design Decisions to Lock Before Drawings Go In
In short: Fix the footprint, height, foundation and energy approach in January, so the permit drawings are drawn once.
Moving a wall on a sketch costs an eraser. Moving it after the permit drawings are filed means revised drawings and another review. That's why these decisions come first.
Decision | Why it has to be fixed before drawings |
|---|---|
Footprint and setbacks | Sets where the house sits and what the zoning review checks |
Height and storeys | Checked against the zoning limit for the lot |
Foundation and basement | Depends on the soil report and drives excavation |
Energy approach | New houses follow Supplementary Standard SB-12 [20] |
Radon rough-in | New houses need a rough-in for a subfloor depressurization system [20] |
Structural spans and large openings | Set beam sizes and engineering on the drawings |
Every permit application filed since April 1, 2025 uses the 2024 Ontario Building Code [21], so plans drawn for an older project may need updating.
The drawings also need the right signature. Building designers in Ontario pass Building Code exams for their area of practice and register with the Province [22], and their Building Code Identification Number (BCIN) goes on the designer form filed with the permit. Architects are registered through the Ontario Association of Architects instead [23].
At Building Dreams, the Design stage covers space planning, architectural coordination, 3D renderings and material selections, with design reviews that keep the plan on scope and budget. For how that compares, see design-build versus separate hiring.
Selections to Make Now
In short: If it shows on the drawings, choose it before they're filed. Finishes can wait.
Not every choice has to be made in winter. The ones that do are the ones the permit file depends on. Under the SB-12 prescriptive path, a new house has to meet a package of insulation, window and mechanical efficiency requirements, and the Energy Efficiency Design Summary filed with the permit has to match the drawings [24]. New house applications also carry heat loss calculations and duct design [25].
Selection | Decide by | Why |
|---|---|---|
Windows and exterior doors | February | Sizes show on the elevations, and window performance is part of the energy package [24] |
Heating, cooling and ventilation | February | Equipment efficiency, heat loss and duct design go in with the permit [24][25] |
Fireplace and venting | February | Affects framing, venting and the mechanical layout |
Kitchen and bath layouts | February | Sets plumbing locations and walls on the floor plans |
Exterior cladding and roofing | February | Shows on the elevations and wall sections |
Interior finishes, fixtures and paint | Later in the build | Can be carried as allowances in the proposal |
Allowances keep the schedule moving without forcing every decision early. In Building Dreams' Plan and price stage, the detailed proposal covers labour, materials and allowances, so the budget has a number for each finish you haven't picked yet.
Give each allowance a decision date, too. A finish chosen late can hold up the trade waiting for it. At Building Dreams, selections and changes are documented as work progresses, so nothing relies on memory.
Contract, Tarion Enrolment and Development Charges
In short: Check the builder's licence, sign the contract once the home is enrolled with Tarion, and budget for development charges at occupancy.
The last winter tasks happen on paper. In Ontario, new home builders must be licensed by the Home Construction Regulatory Authority (HCRA). The Ontario Builder Directory shows a builder's licence status, any conditions on it, warranty claims Tarion has resolved in the past 10 years, and the homes they've built [26].
For a home built on land you already own, which Tarion calls a contract home, the builder has to enrol the home with Tarion before signing the construction contract. The Warranty Information Sheet gets attached to that contract [27]. Ask for both before you sign. Building Dreams also gives its own two-year materials and labour warranty, separate from the statutory coverage.
Development charges moved too. Before November 3, 2025, municipal and regional charges on a new non-rental home were due when the permit was issued. Now they're deferred to the occupancy permit, which can't be issued until they're paid [28]. Municipalities also can't charge interest on that deferral [29].
Payment or step | When it happens |
|---|---|
Tarion enrolment | Before the construction contract is signed [27] |
Building permit fees and education development charges | At the building permit stage [30] |
Municipal and regional development charges | Before the occupancy permit is issued [28] |
Pre-delivery inspection | On or before the possession date [31] |
The charges still belong in the total budget from the start. Only the payment date moved.
Financing, Insurance and Holdback
If a construction mortgage is part of the plan, start the lender conversation in winter too. Lenders using staged draws collect the plans, cost estimates, building contract and permits before funds flow [32]. Ontario's Construction Act also requires an owner to hold back 10% of each payment as work is supplied, which protects against liens from unpaid trades [33]. And confirm in writing who carries builder's risk (course of construction) insurance. The Insurance Bureau of Canada warns that standard home policies are written for occupied homes and may leave gaps during a build [34].
Is Spring the Best Time to Build a House in Ontario?
In short: Spring is a good window once the permit file is complete. Early spring brings road limits and nesting season, so plan the first dig around them.
The best time to build a house in Ontario is the first stretch of workable ground after the permit file is complete. For many lots, that means late April or May.
Early spring has limits of its own. From March 1 to April 30, spring thaw restrictions apply on posted roads [4], and commercial vehicles on those roads are held to 5,000 kg per axle [35]. That can affect concrete trucks, dump trucks and the floats that bring in an excavator. Tree work is also easier to finish before nesting season starts [3].
Before anyone digs, a public utility locate is required. Ontario One Call takes the request at least 5 business days ahead, the service is free, and locates are valid for at least 60 days [36]. If a contractor is digging, make sure they've made the request [36].
Design meetings and paperwork aren't tied to the season. The calendar sets the window, and the paperwork decides whether you're ready for it. A custom home builder in Hamilton who starts the file in December can plan the first dig for the day the roads and the permit both allow it.
Your Custom Home Planning Checklist
In short: Twelve tasks, in order, from the first zoning check to the locate request.
Use this custom home planning checklist to track the winter in one place. Each row points back to a section above.
Task | Target month | Done when |
|---|---|---|
Zoning and setback check | December | You know the setbacks, height and coverage the lot allows |
Conservation authority check | December | You know whether the lot is regulated, and by which authority |
Survey and soil report ordered | December | The surveyor and engineer are booked |
Tree review | December | You know which trees need a permit |
Design-build team chosen | December | The builder's licence is checked in the Ontario Builder Directory |
Floor plan, footprint and height settled | January | The design stops changing size |
Conservation authority and tree permits applied for | January | Applications are filed and confirmed complete |
Permit drawings, grading plan and key selections finished | February | Windows, mechanical system and layouts are on the drawings |
Approved trees removed | February to early March | Removal is done before nesting season |
Variance final and Burlington Pre-Building Approval in hand, if needed | February to March | Every approval the permit depends on is issued |
Contract signed and permit application filed | March | The home is enrolled, the contract is signed and the application is complete |
Locate request placed | April | The request is in at least 5 business days before the dig |
If a row slips, the rows after it slip too. Most of the list can run alongside the design work for custom homes, so the file is ready when the ground is.
How Building Dreams Plans a Spring Start
In short: The winter plan maps onto three of Building Dreams' five stages, and the first conversation is the place to start it.
Building Dreams works in five stages: Discover, Design, Plan and price, Build and communicate, and Handover and support. For a spring start, December is Discover, with a site visit and a talk about priorities, existing conditions, budget and likely timing. January and February are Design, covering space planning, architectural coordination, 3D renderings and material selections. March is Plan and price: the detailed proposal, contract, schedule, permits and procurement, with permit requirements coordinated with the municipality.
Once building starts, daily BuilderTrend updates keep you in the loop. The team works from offices in Hamilton, Burlington and Niagara-on-the-Lake, and builds custom homes in Niagara as well as across Hamilton and Halton. The best time to call is before drawings or major selections are final.
Frequently Asked Questions
In short: Quick answers on timing, permits, trees, Tarion and development charges.
When should I start planning a custom home build?
For a spring 2027 groundbreaking, start in December 2026. A lot that needs a conservation authority permit can take up to 111 days to clear that step [2], and the building permit's 10-day review only starts once every approval is in [1]. Starting in December leaves room for design, drawings and approvals in order.
Can you build a house in winter in Ontario?
Yes. Permit offices review applications year-round, and the 10-day review for a house doesn't change with the season [1]. Ground and road conditions are what limit early-spring sitework, since posted roads carry thaw restrictions from March 1 to April 30 [4]. Winter is the best time to get the permit file complete.
How long does a building permit take for a new house in Hamilton?
Once the application is complete, the Ontario Building Code allows 10 business days for a decision [1]. In Hamilton, applicable law approvals, such as zoning and conservation authority permits, have to be in hand before the application can be accepted [5]. Most of the waiting happens before the application goes in.
Do I need a permit to remove trees before building?
It depends on the city. Burlington requires a permit for private trees 20 cm in diameter or larger in its urban area [17]. Hamilton has no city-wide private tree by-law, but Ancaster and Dundas still have their own [15]. Wherever you build, avoid clearing during the bird nesting season [19].
Does my builder have to enrol my home with Tarion before we sign?
Yes. For a contract home built on your own land, the builder must enrol the home with Tarion before entering into the construction contract, and must attach the Warranty Information Sheet to it [27]. You can check a builder's licence in the Ontario Builder Directory [26].
When are development charges paid on a new home in Ontario?
Since November 3, 2025, municipal and regional development charges on a new non-rental home are paid before the occupancy permit is issued [28]. Before that date, they were due at permit issuance. Building permit fees and education development charges are still paid at the permit stage [30].
Planning a spring 2027 custom home in Hamilton, Burlington or Niagara? Start a home project with Building Dreams to work through your lot, drawings and permit file this winter.
Definition Bank
Term | Meaning |
|---|---|
Complete application | A permit application with every required form, drawing, fee and approval, which starts the review clock. |
Applicable law | Other rules, such as zoning or conservation authority permits, that must be met before a building permit is issued. |
Minor variance | Permission from a Committee of Adjustment to depart slightly from a zoning rule. |
Conservation authority regulated area | Land near water, wetlands or hazards where a conservation authority permit is needed. |
Pre-Building Approval | Burlington's combined zoning, grading and forestry review before a new home's building permit. |
Reduced load period | The spring thaw window when trucks on posted roads carry lighter axle loads. |
Building Code Identification Number (BCIN) | The registration number of a qualified building designer in Ontario. |
Supplementary Standard SB-12 | The Ontario Building Code standard that sets energy efficiency for houses. |
Energy Efficiency Design Summary | The form filed with a permit that shows how a house meets SB-12. |
Contract home | A new home built for the owner on land the owner already holds. |
Tarion enrolment | Registering a new home in Ontario's statutory warranty program before construction. |
Development charges | Municipal and regional fees on new homes that help pay for growth-related services. |
Pre-delivery inspection (PDI) | A walkthrough with the builder on or before possession to record items to fix. |
Public utility locate | Marking of buried utility lines before digging, requested through Ontario One Call. |
Quick Facts
Ontario house permit clock
Property | Value |
|---|---|
Decision period | 10 business days for a house [1] |
Clock starts | Once the application is complete [1] |
Must come first | Applicable law approvals such as zoning and conservation authority permits [1][5] |
Code edition | 2024 Ontario Building Code for applications since April 1, 2025 [21] |
Conservation authority permit
Property | Value |
|---|---|
Regulation | O. Reg. 41/24 under the Conservation Authorities Act [2] |
Completeness check | Within 21 days [2] |
Decision | Within 90 days of a complete application [2] |
If no decision | Appeal to the Ontario Land Tribunal [2] |
Niagara authority | Niagara Peninsula Conservation Authority [11] |
Spring reduced load period
Property | Value |
|---|---|
Dates | March 1 to April 30 [4] |
Axle limit | 5,000 kg per axle on designated roads [35] |
Legal basis | Highway Traffic Act, s. 122 [35] |
Development charge deferral
Property | Value |
|---|---|
Change | Municipal and regional charges deferred to the occupancy permit [28] |
In force | November 3, 2025 [28] |
Interest | Not chargeable on legislatively deferred charges [29] |
Still due at permit | Building permit fees and education development charges [30] |
Building Dreams Contracting Inc.
Property | Value |
|---|---|
Process | Discover, Design, Plan and price, Build and communicate, Handover and support |
Offices | Hamilton, Burlington, Niagara-on-the-Lake |
Updates | Daily BuilderTrend updates during construction |
Warranty | Two-year materials and labour warranty |
Sources
Government of Ontario. Citizen's Guide to Land Use Planning: Building Permits. https://www.ontario.ca/document/citizens-guide-land-use-planning/building-permits
Government of Ontario. Permits under the Conservation Authorities Act. https://www.ontario.ca/page/permits-under-conservation-authorities-act
Environment and Climate Change Canada. Overview of Nesting Periods. https://www.canada.ca/en/environment-climate-change/services/avoiding-harm-migratory-birds/general-nesting-periods/overview.html
City of Hamilton. Truck Route Network. https://hamilton.ca/home-neighbourhood/getting-around/driving-traffic/truck-route-network
City of Hamilton. Applicable Law Checklist, April 2025. https://hamilton.ca/sites/default/files/2025-04/buildingpermit-checklist-applicable-law-apr2025.pdf
City of Hamilton. Building Permit Application Requirements. https://www.hamilton.ca/build-invest-grow/construction-renovation/residential-building-renovation/building-permit
Government of Ontario. Planning Act, R.S.O. 1990, c. P.13, s. 34(1.4), s. 45(4) and s. 45(12). https://www.ontario.ca/laws/statute/90p13
City of Burlington. Zoning Clearance Application Form (Pre-Building Approval note). https://webforms.burlington.ca/Planning-and-Building/Zoning-Clearance-Application-Form
City of Burlington. 2026 Pre-Building Approval Application Fees, effective January 1, 2026. https://www.burlington.ca/en/planning-and-development/resources/Zoning-Clearance-Certificates/2026-Fee-Schedule-PBA.pdf
City of Niagara Falls. Building Permit Application Process. https://niagarafalls.ca/building-planning-and-business/building-and-renovating/building-permit-application-process/
City of Niagara Falls. Application for a Permit to Construct or Demolish, with Applicable Law Checklist. https://niagarafalls.ca/media/x2qf0qnd/application-for-a-permit-to-construct-or-demolish-ministry.pdf
Government of Ontario. O. Reg. 545/06, Zoning By-laws, Holding By-laws and Interim Control By-laws, s. 1.1. https://www.ontario.ca/laws/regulation/060545
Government of Ontario. O. Reg. 254/23, Prescribed Areas. https://www.ontario.ca/laws/regulation/230254
City of Hamilton. Zoning Compliance Review. https://hamilton.ca/build-invest-grow/planning-development/zoning/zoning-compliance-review
City of Hamilton. Private Trees. https://services.hamilton.ca/home-neighbourhood/house-home/gardens-trees/private-trees
City of Hamilton. Engage Hamilton: Harmonized Private Tree By-law. https://engage.hamilton.ca/harmonizedprivatetreebylaw
City of Burlington, media release reposted by the Office of the Mayor. New Online Guide Available to Help Navigate Tree Protection and Tree Permits in Burlington. https://www.mariannemeedward.ca/posts-to-be-added/new-online-guide-available-to-help-navigate-tree-protection-tree-permits-in-burlington
Town of Fort Erie. Tree Protection Guidance Manual. https://www.forterie.ca/Guidance-Manual-V2-AODA.pdf
Environment and Climate Change Canada. Guidelines to Avoid Harm to Migratory Birds. https://www.canada.ca/en/environment-climate-change/services/avoiding-harm-migratory-birds/reduce-risk-migratory-birds.html
Home Construction Regulatory Authority. Ontario Building Code Updates. https://www.hcraontario.ca/resources/ontario-building-code-updates
Government of Ontario. The 2024 Ontario Building Code. https://www.ontario.ca/page/2024-ontario-building-code
Government of Ontario. Become a Registered Building Practitioner. https://www.ontario.ca/page/become-registered-building-practitioner
City of Welland. Schedule 1: Designer Information. https://www.welland.ca/building/devForms/DESIGNER.pdf
Township of Alnwick/Haldimand. Energy Efficiency Design Summary (Part 9 Residential), provincial form. https://www.ahtwp.ca/s/Energy-Efficiency-Design-Summary.pdf
Municipality of Central Elgin. New Housing Application, 2026. https://www.centralelgin.org/Building-Permits/New-Housing---Application_2026_FillablePDF.pdf
Government of Ontario. What to Know Before Buying a Home. https://www.ontario.ca/consumers/buying-home
Tarion. Requirements for Purchase Agreements. https://tarion.com/node/756
Ontario Building Officials Association. Ontario CodeNews, Issue 373, November 3, 2025. https://www.oboa.on.ca/news/ontario-codenews-issue-373-november-3-2025
Ministry of Municipal Affairs and Housing. Letter on Bill 17 and Deferred Development Charges, November 28, 2025. https://www.amo.on.ca/sites/default/files/assets/DOCUMENTS/Letters/2025/MMAH-LTR-AP-Bill-17-DC-Freezes-2025-11-28.pdf
Ontario Large Municipalities Chief Building Officials and Ontario Building Officials Association. Development Charge Deferrals to Building Occupancy, October 31, 2025. https://www.collingwood.ca/media/file/olmcbooboaindustrydc-letteroct-31-202592pdf
Tarion. Building Your Dream Home? Five Things to Expect from Your Builder. https://tarion.com/node/65973
Canada Guaranty Mortgage Insurance Company. Progress Draw Advantage. https://www.canadaguaranty.ca/progress-draw-advantage/
Government of Ontario. Construction Act, R.S.O. 1990, c. C.30, s. 22(1). https://www.ontario.ca/laws/statute/90c30
Insurance Business Canada. Spring renovation boom exposes coverage gaps in standard home policies (reporting Insurance Bureau of Canada guidance). https://www.insurancebusinessmag.com/ca/news/construction/spring-renovation-boom-exposes-coverage-gaps-in-standard-home-policies-571391.aspx
Government of Ontario. Highway Traffic Act, R.S.O. 1990, c. H.8, s. 122. https://www.ontario.ca/laws/statute/90h08
Ontario One Call. Homeowners: Public Utility Locates. https://ontarioonecall.ca/homeowners/